TOWNSVILLE RING ROAD STAGE 5
Georgiou delivered the design and construct contract for the Bruce Highway-Townsville Ring Road Stage 5 project, by the Department of Transport and Main Roads (DMTR).
Client
Department of Transport and Main Roads
Location
Townsville Queensland 4810, Australia
Duration
Mid 2021 - Late 2023
Cost
$233 million
Georgiou delivered the design and construct contract for the Bruce Highway-Townsville Ring Road Stage 5 project, for the Department of Transport and Main Roads.
The $233 million project involves the duplication of the remaining 5.2km, two-lane undivided section of the Townsville Ring Road between Vickers Bridge and Shaw Road.
Aside from duplication the remaining 2-lane section of the Townsville Ring Road, the team will complete the appropriate bridges and drainage for flood mitigation, lighting, intelligent transport systems, noise mitigation measures and environmental protections.